Guide 03 · Destination
Shipping a used tower crane to Nigeria.
The crane is the easy part. Form M, PAAR, SONCAP and the duty build-up are where the money and the months go, and a single sequencing error — opening Form M after the vessel sails — turns a three-week clearance into a ten-week one at your cost. Plan 8 to 14 weeks door to site, and hold 20 to 25 % of the CIF value for duty.
The short version
- 30 to 42 days on the water, and 8 to 14 weeks from contract to machine on site. Clearance is the leg that most often doubles.
- Form M must be opened before the vessel sails. PAAR is built on it, and there is no way to recover the time once the ship has left.
- Budget 20 to 25 % of CIF for duty, levies and VAT — VAT is charged on the duty-inclusive value, not on CIF alone.
- A tower crane is not a container job. 10 to 12 m jib sections and 2.5 t counterweight blocks move as breakbulk or out-of-gauge flat rack.
- A load-port survey is the cheapest line in the shipment. Half a day of a surveyor beats three weeks of demurrage on a crane with a missing mast section.
On this page
The four things that decide the timeline
- Form M, opened before shipment. Everything downstream depends on it. There is no workaround.
- PAAR, obtained before arrival. The customs valuation and classification document. Your agent applies; you supply the documents.
- Conformity certification where the product schedule requires it. Check the current SONCAP product list for cranes before you assume either way.
- Berth and dwell time at Lagos. Apapa and Tin Can Island are congested by design; Lekki Deep Sea Port has changed the picture for some cargo but service coverage for breakbulk needs confirming case by case.
Route and vessel type
Chinese loading ports for this trade are Tianjin Xingang and Qingdao. Both have heavy-lift capacity, both handle breakbulk, and both ship to West Africa on regular liner and semi-liner services.
| Leg | Detail |
|---|---|
| Load port | Tianjin Xingang or Qingdao |
| Discharge port | Apapa or Tin Can Island, Lagos; Onne or Port Harcourt for oil and gas projects; Lekki for suitable services |
| Ocean transit | Typically 30 – 42 days, via Suez or via Singapore–Durban depending on service |
| Vessel mode | Breakbulk or out-of-gauge flat rack; containers only for mast bundles and component cases |
| Cargo profile, 80 m jib crane | Roughly 40 – 50 t across 30 – 60 packages, 180 – 250 m³, with jib sections 10 – 12 m long |
The reason a tower crane is not a container job is geometric. A mast section is roughly 1.6 to 2.0 m square and 3 m long — a bundle of them fits a 40 ft box. A jib section is 10 to 12 m and will not load efficiently through a container door. A counterweight block is 2.5 to 3.5 t of dense cast iron that should never be stacked on general cargo. So the realistic mix is breakbulk for the jib and counterweights, containers for mast bundles, electrical panels, rope and small components.
The stow plan is not paperwork
Ask for the stow plan before loading and read it. What matters:
- Cradles under jib sections, not direct slinging on the chord. Point loading on a hollow chord is how a jib arrives bent.
- Separation between painted steel surfaces, because thirty-five days of low-amplitude vibration against another steel face removes paint and starts corrosion cells.
- Counterweight low and central, with lashings rated for the actual mass, not for the package weight on the manifest.
- Machined faces — slew ring, pin bores, rope drums — blanked and greased, and photographed as blanked.
- Package numbering matching the packing list, so that a missing item is identified at the load port and not at Apapa.
The Nigerian document chain, in order
These documents are sequential. Getting them out of order is what creates the delay.
| # | Document | Issued by | When |
|---|---|---|---|
| 1 | Proforma invoice | Seller | Before Form M |
| 2 | Form M | Importer, via authorised dealer bank | Before shipment |
| 3 | Commercial invoice, stating used condition, year and serial | Seller | Before shipment |
| 4 | Packing list with per-package weight, dimension and mark | Seller | Before shipment |
| 5 | Certificate of origin / CCVO | Chamber of commerce in the exporting country | Before shipment |
| 6 | Product certificate and SONCAP certificate, where the product schedule requires it | Accredited inspection body | Before shipment — verify applicability |
| 7 | Bill of lading | Carrier | On loading |
| 8 | Insurance certificate, ICC (A) recommended | Buyer's insurer | Before loading |
| 9 | PAAR | Nigeria Customs Service, via clearing agent | Before vessel arrival |
| 10 | Single Goods Declaration and duty payment | Clearing agent | On arrival |
| 11 | Terminal delivery order and release | Terminal / shipping line | After duty |
| 12 | Gate pass and inland haulage | Terminal / haulier | Last |
Two of these deserve emphasis. Form M is opened by the importer, not the exporter — the Nigerian buyer must have a registered company, a tax identification number and a bank relationship. If you are buying your first machine, start the company paperwork before you start shopping. And the CCVO is issued in China, not Nigeria, by the chamber of commerce, so it has to be requested from the seller early; it cannot be produced at Apapa.
The duty build-up
Tower cranes classify under HS 8426.20. The Nigerian import charge is built in layers, and the layering matters because VAT is charged on the duty-inclusive value, not on CIF alone.
| Layer | Applied to | Planning figure |
|---|---|---|
| ECOWAS CET duty on HS 8426.20 | CIF value | 5 % — verify current CET rate |
| Port development and related levies | CIF value | ≈ 8 – 9 % combined |
| VAT | CIF + duty + levies | 7.5 % |
| Effective total | — | Budget 20 – 25 % of CIF |
The other half of the duty question is valuation. Customs assesses the transaction value and may reject a declared figure it considers low, then revalue upward. On used machinery your defence is documentary: the original purchase invoice, nameplate photographs showing model and year, a condition report, and evidence of comparable transactions. Buyers who under-declare to save duty routinely spend two months proving a point and paying storage.
Realistic timeline
| Stage | Duration | Notes |
|---|---|---|
| Contract, Form M, payment instrument | 1 – 3 weeks | Buyer-side; the usual bottleneck |
| Inspection at seller's yard | 1 – 2 days | Before dismantling |
| Dismantle, pack, load to truck | 5 – 10 working days | Mobile crane on site |
| Inland to port, export declaration | 3 – 7 days | Allow for a customs inspection slot |
| Loading and lashing | 2 – 4 days | Plus vessel waiting time |
| Ocean transit | 30 – 42 days | Routing dependent |
| Nigerian clearance | 2 – 4 weeks | Assumes Form M and PAAR already done |
| Inland haulage, unloading, erection | 1 – 2 weeks | Needs a 50 – 100 t mobile crane |
| Door to site | 8 – 14 weeks | Clearance is the variable |
What buyers get wrong, in frequency order
- Form M opened after the vessel sails. Costs weeks, always at the buyer's expense, never recoverable.
- No budget for the erection crane. A 78 m free-standing tower crane needs a substantial mobile crane to erect. It is often the largest line after the machine and is almost never in the first budget.
- Buying more free-standing height than the site permits. Then discovering at the permit stage that the configuration has to change, which means different mast counting and different foundation.
- Assuming a CIF price includes the port. Terminal handling, agency, storage and demurrage are all yours. See FOB vs CIF.
- Shipping without a load-port survey. The missing component is found at Apapa, where it cannot be replaced and where the crane is now unusable.
- No packing list with per-package weights. Terminal handling charges and lashing design both depend on it, and reconstructing it after loading is guesswork.
What we need from you to quote a delivered machine
We quote per order rather than publishing a price, because the honest number depends on configuration, documentation and terms. Five inputs get you a costed answer instead of a range:
- Heaviest routine lift, at what radius, at what height.
- Discharge port and whether you want FOB or delivered terms.
- Whether you already have a clearing agent and a Form M channel.
- Timeline — is there a foundation date driving this?
- Whether you need erection support or only the machine.
The two large-crane records are documented unit by unit, with nameplates and certificates photographed: ZOOMLION T600-32U (16 t per trolley, 6,800 kN·m, 80 m jib) and XCMG XGT8040-25 (25 t, 525 t·m, built 2019, both certificates photographed). The stock page lists all 133 units in eight groups.
Frequently asked
How long is the sea leg to Lagos?
Typically 30 to 42 days from Tianjin Xingang or Qingdao, depending on routing and transhipment. Door to site is realistically 8 to 14 weeks, and clearance is the variable that most often doubles.
Do I need Form M before shipment?
Yes. It is opened by the Nigerian importer through an authorised dealer bank and registered before shipment, because PAAR is built on it. Opening it after the vessel sails is the most common cause of demurrage at Apapa.
What is PAAR, and who applies?
The Pre-Arrival Assessment Report, issued by Nigeria Customs Service. Your licensed clearing agent applies using the Form M, invoice, bill of lading, packing list, certificate of origin and any conformity certificate. Obtain it before arrival.
How much duty on a used tower crane?
Budget 20 to 25 % of CIF. That combines the CET rate on HS 8426.20, import levies, and 7.5 % VAT charged on the duty-inclusive value. Confirm the current computation with a licensed agent before committing to a landed-cost budget.
Can it go in a container?
Partly. Mast sections bundle into 40 ft boxes and small components travel in cases, but 10 to 12 m jib sections and 2.5 t counterweight blocks move as breakbulk or out-of-gauge flat rack, with surcharges and an agreed stow plan.
What if customs disputes the invoice value?
They may revalue upward, which raises duty and holds the cargo. Your defence is documentary: original invoice, nameplate photographs, condition report, comparables. Under-declaring converts a two-week clearance into a two-month one.